Friday, April 26, 2002   4/26/02

Our first partial bid came in. From Mike and Heraldo.

job hours cost start finish
framing rough in        
plumbing 12 276 5/1 5/4
3" pvc 200' 8 68    
2 toilet lines in and out 3 280    
2 bath tubs   185    
water heater 50 gal   28    
10 cut valves   45    
10 supply valves        
1st fl elec ruff in 16   5/5 5/7
2nd fl elec ruff in 16   5/8 5/10
1st fl insul 8 749.36 5/11 5/12
2nd fl insul 10 969 5/12 5/13
1st fl sheet rock 25 714 5/14 5/18
2nd fl sheet rock 29 816 5/18 5/21
tape 10 rools 12 30    
mud 5 boxes 1st fl 12 25 5/25 5/26
2nd fl mud     5/26 5/27
paint 1st fl 10 cans 16 150 5/28 5/30
paint 2nd fl 15 cans 18 225 5/31 6/2
tile 1st fl 55 boxes 16 840 6/3 6/5
tile 2nd fl 55 boxes 16 840 6/6 6/8
elec trim out 1st fl 16   6/9 6/10
elec trim out 2nd fl 16   6/11 6/12
int trim        
ext trim        
decks        
hvac        
misc        
249 6,240.36    

Comments - So we're missing the framing on this bid, but Mike's bringing his framer
Saturday morning to complete the estimate. He only wants one floor but
will finish the whole place in a month and a half. Which would enable us
to rent out one floor or do another work trade on the first floor.

The costs look reasonable. He's showing us an
8,000 square job he did recently where he did all the electric, plumbing
and sheetrock.

But we definitely need to get the framing, trim, decks, hvac, etc totals to have a complete picture.