| job | hours | startdate | finishdate | first floor | 1,472 | |
| framing 1f | 2nd fl | 1,472 | ||||
| framing 2f | lofts | 380 | ||||
| framing exterior | total | 3,324 | ||||
| 5 | electrical rough in 1f | 10 | 5/11/2002 | 5/12/2002 | cottage | 768 |
| 6 | electrical rough in 2f | 10 | 5/12/2002 | 5/13/2002 | efficiency | 216 |
| 1 | plumbing roughin | 12 | 5/1/2002 | 5/2/2002 | total | 4,308 |
| 2 | plumbing trim | 8 | 5/3/2002 | 5/3/2002 | ||
| 9 | insulation 1f | 8 | 5/14/2002 | 5/15/2002 | ||
| 10 | insulation 2f | 10 | 5/16/2002 | 5/17/2002 | ||
| 11 | sheetrock 1f | 25 | 5/18/2002 | 5/20/2002 | ||
| 13 | tape 1f | 4 | 5/25/2002 | 5/25/2002 | ||
| 14 | mud 1f | 4 | 5/25/2002 | 5/25/2002 | ||
| 12 | sheetrock 2f | 32 | 5/21/2002 | 5/21/2002 | ||
| 15 | tape 2f | 4 | 5/26/2002 | 5/26/2002 | ||
| 16 | mud 2f | 4 | 5/26/2002 | 5/26/2002 | ||
| inside trim 1f | ||||||
| inside trim 2f | ||||||
| outside trim | ||||||
| doors 1f | ||||||
| doors 2f | ||||||
| 4 | decks 1st and 2nd fl | 32 | 5/7/2002 | 5/10/2002 | ||
| 3 | siding touch up | 24 | 5/4/2002 | 5/6/2002 | ||
| paint outside | ||||||
| 15 | paint inside 1f | 16 | 5/27/2002 | 5/28/2002 | ||
| 16 | paint inside 2f | 18 | 5/29/2002 | 5/31/2002 | ||
| 7 | hvac 1st fl | 10 | ||||
| 8 | hvac 2nd fl | 10 | ||||
| 17 | floors wood or tile 1f | 24 | 6/1/2002 | 6/3/2002 | ||
| 18 | flloors wood or tile 2f | 24 | 6/4/2002 | 6/7/2002 | ||
| total hours | 289 | |||||
| item | units | cost | total | |||
| plumbing parts | 1 | 276.00 | 276.00 | |||
| 3" pvc 20' pipes | 10 | 6.80 | 68.00 | |||
| toilets | 2 | 74.00 | 148.00 | |||
| 2 toilet lines in and out | 2 | 140.00 | 280.00 | |||
| 2 bath tubs | 2 | 140.00 | 280.00 | |||
| 2 sinks | 2 | 34.00 | 68.00 | |||
| cut valves | 10 | 4.50 | 45.00 | |||
| supply valves | 10 | 4.50 | 45.00 | |||
| 3/4 copper conduit feet | 100 | 1.20 | 120.00 | |||
| 1/2 copper conduit feet | 50 | 0.80 | 40.00 | |||
| toilet rings | 2 | 5.00 | 10.00 | |||
| water heater 50 gal | 2 | 185.00 | 370.00 | |||
| electrical | 1 | 500.00 | 500.00 | |||
| hvac second floor | 2 | 3,000.00 | 6,000.00 | |||
| 1st fl insul | 1 | 749.36 | 749.36 | |||
| 2nd fl insul | 1 | 969.00 | 969.00 | |||
| 1st fl sheet rock | 1 | 714.00 | 714.00 | |||
| 2nd fl sheet rock | 1 | 816.00 | 816.00 | |||
| tape | 10 | 3.00 | 30.00 | |||
| mud boxes | 5 | 5.00 | 25.00 | |||
| paint 1st fl cans | 10 | 15.00 | 150.00 | |||
| paint 2nd fl cans | 15 | 15.00 | 225.00 | |||
| tile first fl | 55 | 15.27 | 839.85 | |||
| tile 2nd fl | 55 | 15.27 | 839.85 | |||
| wolm 2x6x16 | 128 | 11.78 | 1,507.84 | |||
| wolm 2x4x16 | 80 | 7.87 | 629.60 | |||
| total | 15,745.50 | |||||
| 1x4x16 | 80 | 5.31 | 424.80 | |||
| z flashing | 4 | 1.00 | 4.00 | |||
| 8 pitch base | 8 | 3.00 | 24.00 | |||
| paint, caulk & nails | 1 | 0.00 | 0.00 | |||